Employees
To assign people to projects and let each worker log hours in Procore, Procore needs to know the employees. HR data stays in ComputerEase.
Scope of Work
This document describes how Bic Electric works today, how it will work with Procore, and what the connector does between the two systems. It closes with the open questions we need to resolve with you and with Deltek before we start.
How Bic Electric works today
Bic Electric delivers protection and control, substation construction and fiber projects. Four areas touch project data.
Protection & Control, Substation Construction, Fiber Services and Field Project Management. They deliver the projects and log their hours.
Coordinates between the field and finance. Defines project data and tracks performance and billing.
Creates and updates projects in ComputerEase, reconciles expenses, bills customers and prepares reporting.
Employee data stays in ComputerEase. CoAdvantage processes payroll.
The PMO sends Finance a template with the project data, its phases and the estimate by cost type (labor, overtime, per diem, travel time…). Finance re-enters it in ComputerEase. Projects move through Planned, Active and Closed, and only accept hours and costs while Active.
Field staff log their hours in the ComputerEase mobile app. The PMO follows progress in the work-in-progress report.
Hours go to CoAdvantage, which processes payroll. The cost flows back to the jobs in ComputerEase.
Employees log their corporate card expenses in ComputerEase with the receipt. Accounting matches them one by one against the bank and posts them day by day.
Customer invoices are prepared and printed by hand.
An Excel workbook is fed by three ComputerEase exports: contract, billed, pending billing, labor and other costs, plus a calculated projection.
From our sessions with Finance and the PMO. We record these as a starting point for future improvements.
The PMO fills an Excel sheet, Finance creates the job and sends back a project number, and the same sheet goes back and forth again when the PO arrives.
Field crews sometimes reach a site before the project is active in ComputerEase, and the PMO has to wait for Finance to activate it.
Some crews log hours in the ComputerEase app. Others send a weekly spreadsheet that the PMO reviews and passes to Finance at month end.
There are no dates per phase and no assigned crew, so anyone can charge hours to any project.
Progress comes from weekly meetings. The PMO checks the remaining contract, calculates the amount and emails Finance. Invoicing a remainder can mean going back through months of folders.
Accounting applies each contract's per diem and travel rates manually before creating the invoice.
The PMO cannot see whether an invoice was sent, corrected or paid without chasing Finance, while the field keeps asking.
The profitability report is refreshed weekly and takes 30 to 60 minutes to update by hand, with no alerts.
Every receipt is checked by hand against the bank, reclassified when needed and posted day by day. It delays every month-end close.
The foundation
The connector puts Procore and ComputerEase data in one place. It is the foundation for automating the steps above one by one. This estimate shows what that time costs today, with conservative assumptions you can adjust.
Potential yearly saving
$164,320
Field $60,320Office $104,000
That is the working time of 2.0 full-time people, every week, spent on manual steps.
How it will work with Procore
Procore becomes the system of work for projects. ComputerEase keeps accounting, employees and payroll. The connector moves each piece of data in one direction, from its system of record.
| Who | Today | With Procore and the connector |
|---|---|---|
| PMO and project managers | Prepare a template so Finance can create the project. | Create the project, budget, schedule and change orders in Procore. |
| Field staff | Log hours in the ComputerEase app. | Log hours in Procore, only on the projects they are assigned to. |
| Finance | Re-enters every project and every change. | Reviews and imports the job prepared by the connector. |
| Accounting | Prepares invoices by hand. | Imports the invoices issued in Procore. Payroll stays the same. |
| Management | Checks a manually updated Excel file. | Sees actual cost and billing for each project in Procore. |
End-to-end process · BPMN 2.0
The diagram follows a project from its creation in Procore until its invoice is recorded in ComputerEase. Click any step to see what happens and in which system.
On small screens, swipe the diagram sideways.
What the connector syncs
Each piece of data has a system of record and travels in one direction only. Connections marked Accounting review wait in ComputerEase until accounting reviews them; Automatic ones apply on their own.
To assign people to projects and let each worker log hours in Procore, Procore needs to know the employees. HR data stays in ComputerEase.
Budgets, hours and costs must be classified the same way in both systems. Otherwise a project's numbers never match.
Costs shown in Procore must be tied to the same vendor as in accounting.
Accounting needs the project in ComputerEase to record payroll, invoices and costs against it. This replaces the template the PMO sends Finance today to re-enter by hand.
If the budget or the contract value changes in Procore, accounting must see the same figure.
Payroll is still calculated in ComputerEase with CoAdvantage, so the hours logged in Procore have to reach it.
Project managers need to see in Procore what each project has actually spent (processed payroll, vendors and other costs), not just the budget.
Fuel, meals and travel paid with company cards are project costs, and project managers need to see them.
The invoice is prepared in Procore with the project's real progress, but accounting is still kept in ComputerEase.
Open questions
Grouped by topic. Each question shows who it is for.
Workaround: Each file the connector sends waits in the API Management queue until a user imports it. We treat this as an accounting review step, and the console flags anything pending.
Milestones and deliverables
Each milestone ends with an acceptance test by Bic Electric.
Access, a proof of concept on both APIs, technical design and the connector foundation deployed.
| 1.1 · Planning, infrastructure and automated deployment | $1,400 |
| 1.2 · Procore and ComputerEase connectors and sync engine | $2,100 |
| 1.3 · Operations console and alerts | $1,050 |
Acceptance: The connector is deployed in test, authenticated in both systems, with a real import processed in ComputerEase.
ComputerEase catalogs and employees in Procore, and every Procore project created and updated in ComputerEase.
| 2.1 · Employees from ComputerEase to Procore | $1,750 |
| 2.2 · Cost codes, cost types, vendors and project sync | $1,575 |
| 2.3 · Budget changes and change orders from Procore to ComputerEase | $2,800 |
| 2.4 · Initial load of active projects | $875 |
| 2.5 · Integration and acceptance testing | $2,100 |
Acceptance: A project created in Procore appears in ComputerEase with its phases and budget, and the ComputerEase catalogs are in Procore.
Approved hours from Procore into ComputerEase payroll, and actual cost and expenses back in Procore.
| 3.1 · Approved hours from Procore to ComputerEase | $2,800 |
| 3.2 · Actual project cost from ComputerEase to Procore | $2,450 |
| 3.3 · Card expenses from ComputerEase to Procore | $1,400 |
| 3.4 · Nightly reconciliation and variance report | $875 |
| 3.5 · Parallel payroll cycle | $1,050 |
Acceptance: A full payroll cycle with Procore hours reconciles with ComputerEase.
Customer invoices issued in Procore recorded in ComputerEase, with tracking.
| 4.1 · Customer invoices from Procore to ComputerEase | $1,400 |
| 4.2 · Import tracking, alerts and parallel month-end close | $1,575 |
Acceptance: A parallel month-end close with Procore invoices recorded in ComputerEase.
End-to-end testing with real data and production rollout with phased activation.
| 5.1 · End-to-end testing | $1,400 |
| 5.2 · Production deployment and phased activation | $1,750 |
Acceptance: The system is in production after a successful end-to-end test with real data.
Timeline
Work starts on December 1, 2026. Weekends and US holidays are excluded.
Investment
Prices include the 60-day warranty and do not include Procore or Deltek licenses, connector hosting costs or taxes.
| Milestone | Amount |
|---|---|
| M1 · Connector platform | $4,550 |
| M2 · Master data and projects | $9,100 |
| M3 · Hours and actual cost | $8,575 |
| M4 · Customer billing | $2,975 |
| M5 · Final testing and go-live | $3,150 |
| Total scope | $28,350 |
Warranty
Once the integration is in production and fully delivered, Bic Electric has 60 days of free support for any issue with it, for as long as each issue takes to resolve. The warranty is included in the price of this Scope of Work.
Any error or unexpected behavior in the connections, the console or the alerts delivered in this scope, plus help for your team while the new process settles in.
Issues are reported by email to NimbusPC and handled by the same team that built the integration, until they are resolved.
New connections or features outside this scope. Those are quoted separately.
Support and maintenance
An integration depends on two systems that keep changing. These plans start after the warranty and keep the connector running, secure and up to date. Prices in US dollars, billed monthly.
| What's included | Essential Care$199per month | Premium Care$499per month |
|---|---|---|
| 24/7 monitoring of the connector and every sync | ✔ | ✔ Priority |
| Emergency support | ✔ | ✔ Priority |
| Bug fixes for the delivered connections | ✔ | ✔ |
| Adjustments when Procore or Deltek change their APIs | ✔ | ✔ |
| Security maintenance | Patches, dependency updates and vulnerability fixes | ✔ Advanced: adds vulnerability scans, credential rotation and access reviews |
| Server maintenance | System updates and resource monitoring | ✔ Advanced: adds capacity tuning, log management and restore tests |
| Monthly health review | ✔ | ✔ |
| Priority support | — | ✔ |
| Sync performance optimization | — | ✔ |
| Backups of the connector database and configuration | — | ✔ |
| Included development hours | 2 per month | 6 per month |
| Discount on additional hours | — | 30% |
Future proposal
Outside the current scope. With Procore and ComputerEase connected, the data is in one place and these improvements can be scoped separately.
A dashboard per project and phase with contract, billed, pending billing, cost, margin and projection. It updates itself from the connector data, with no exports.
Solves: the hand-fed spreadsheet and project-by-project reviews.
Billed and cost against contract
BilledCostIllustrative example
Rules over the data in both systems that notify the right person when something happens, grouped by type of problem.
Solves: weekly meetings just to find out how each project is going.
Illustrative example
AI reads each receipt, splits the items and matches it to the bank transaction. Accounting only reviews what does not match and posts in batches.
Solves: the one-by-one review that stretches every month-end close.
Illustrative example